Potrero Gateway Project Schedule as of March 29, 2024

The SF Public Works contract with Bauman Inc was scheduled to end March 30, but due to rain, street light replacement issues, the project it tasking longer.

The latest schedule, which is APPROXIMATE was emailed to me by Alex Murillo, DPW.

I spoke to the irrigation subcontractor on site March 28 who told me he was checking out the plans.

OPEN GARDEN EVENT

Open Garden this Saturday
June 17 from 2pm to 4pm
400 BLock vermotn Street

FLYER

Join the Eco-Patch team and see how the CA Native Plants are dong these last dry months. They has a good watering in the winter. Come see how they are doing. What will we have for you to do?

  • If you download iNaturalist to your mobile phone, we’ll show you how to use it in the hillside.
  • We encourage you to look at the plants that have survived a drought and then a rainfall and we’ll tell you all about them.  Some will work well in  your backyard.
  • We will have some possibly home-made refreshments for you to share.
  • .We will provide paper bags for weeds that you are able to pull out  if you are so inclined.
  • Depending on who comes to help, we may have other tasks for you!
  • We have four rescued  Douglas Iris, that need a home
Rescued Douglas Iris that need a home

Eco-Patch Open Garden

Flyer for the November 19th event: FLYER

Sunday November 19th from 10am-12pm

IIdiko Polony, Executive Director of Sutro Stewards will be our featured speaker. Learn about Sutro Stewards work and their nursery, a source for Eco- Patch plants and about the Plants for Birds program. Come to see the autumn beauty and seed bounty of local native plants that have had minimal water.

We will be handing out one of the four recommended plants.

Checlk out the four recommended plants using the QR code below:

Eco-Patch Workday – January 9, 2022

Reduced in number by COVID caution, volunteer Eco-Patch members spend a beautiful Sunday morning carrying in mulch and weeding the patch. The December heavy rains were appreciated by the SF Native plants, responding by looking green and healthy. Of course the oxalis responded as well. The GBD mowed ssown some of the surrounding weeds. Adding a mulch pathway around the entiree patch will keep the weeds away as well as maing it easier for folks to walk around and see how the plants are doing. The photos below tell the story too.

Goodbye Pink Flags!

The Eco-Patch is growing! It’s time for the pink flags identifying the plant scientific name to be removed. The Admiral butterfly will not find much nutrition in the flags. Our advice to the butterfly is stick to the plants!
Check out the news from the field collective

Photos by Alex Harker

First Community Meeting – Feb 27, 2013

To kick off the Potrero’s SF MUNA group’s efforts to revitalize the Vermont/ San Bruno freeway area and turn it into a community park space the steering committee held the first planning meeting on February 27, 2013 at The Russian Gospel Church on 17th Street in San Francisco. Neighbors from the community were informed about the meeting via in-person conversations and a flyer drop.

Who attended: In addition to neighbors from Utah, San Bruno, Vermont, Mariposa and 17th Street there was representation from Lorena Wong, Caltrans landscape engineer, Chris Balingit, Caltrans District 4 Maintenance Manager, Jerad Weiner, DPW Community Liason, Alex Medina, Mission Police and Steve Schweigert, SF Parks Alliance.

Our Journey: The Community Planning Meeting is the culmination of almost two years of work by the steering committee that was formed to respond to concerns by the neighborhood for an improvement to the right-of-way area. Initial outreach resulted in help from UC Berkeley’s landscape program which (under the direction of Walter Hood) used the right-of-way area as the design topic for the University’s Thomas Church Memorial Competition. The result was an inspiring set of ideas for improving the area. Following that, the committee interviewed landscape architects and selected Sarah Moos and Marcel Wilson of Bionic (because of their commitment to the public process as a rich source of input and collaboration for making design better) to help create a master landscape plan for the area through a series of community meetings. They worked with the group to produce a marketing brochure for fundraising to support the design process which will involve neighbors.

Where we are right now: Currently the project has raised 10k of its 15k needed to reach its funding goal, which will enable the landscape architect design. After the design phase is complete, taking into consideration the feedback from the community, the committee will need to fundraise for the construction phase, currently estimated at around 100k.
During the meeting a presentation was made by steering committee members: Dianne Bates, Sheldon Trimble, Umesh Bhandary and Jean Bogiages. The presentation can be found at http://sfmuna.org/wp-content/uploads/2011/12/Potrero-Gateway-Park.pdf. During and after the presentation, the audience was asked to contribute their concerns and ideas for the park, which were:
• Design goals
o Highest level considerations: Safety; low maintenance; frequent use; visually appealing
o Design should be uninhabitable for homeless, no hiding places
• Space Requests:
o Lots of lights
o Dog park
o Sprinklers – irregular sprinklers for irrigation and to deter homeless
o More trees to beautify, reduce pollution and decrease freeway sound
o Trees with a high canopy and lower growing ground cover (deters homeless)
o Open or community garden – or corporate sponsored gardens
o Fence to the freeway, open up the space
o Benches on the hillside with ridges (so you can’t lay down)
o Walking paths
o Park fitness equipment (increases use)
o Solar panels (b/c they deflect noise) and trial for alternative energy
o Round wall similar to El Camino
o Combine green material with hardscape materials: decomposed granite paths
o Sidewalk changes: Wider sidewalk on 17th , complete sidewalk on San Bruno
• Other:
o Traffic calming for Vermont and San Bruno, including speed signs, parking changes, bulls eye mirror, permit parking on Vermont
o Neighbors need to occupy/use the space; be there on a weekly/ bi-weekly basis for clean-ups.
o Community neighborhood watch groups by block

Folks were asked to volunteer for the steering committee and to help with fundraising.

Result of meeting: As a result of the meeting, neighbors are more aware and engaged around the project. In addition, the Russian Gospel Church offered their space for continual use by the steering committee and Caltrans sent a follow up note to the steering committee lead saying “It is evident that the community takes great pride in their neighborhood and are looking for feasible solutions and a design that is inviting, aesthetically pleasing, low maintenance and functional.”

Next Steps: The next planning meeting will be the steering committee and the landscape architects. Following that, we have planned two community meetings with the landscape architects to agree on a master landscape plan.

The committee is grateful to the Russian Gospel Church for its willingness to sponsor this first community meeting and the design meetings which will follow.